Pakistan: IFRS S1 and S2, in three phases
July 1, 2025 · Phase I
Larger listed companies meeting any two of: turnover above Rs 25 billion in each of the last two financial years; more than 1,000 permanent and contractual employees; total assets above Rs 12.5 billion.
July 1, 2026 · Phase II
Listed companies meeting any two of: turnover above Rs 12.5 billion in each of the last two financial years; more than 500 permanent and contractual employees; total assets above Rs 6.25 billion.
July 1, 2027 · Phase III
All other listed companies, and non-listed public-interest companies licensed or registered with SECP.
Year one: the report can be published separately, within nine months of your financial year-end. After that, it sits in the annual report, after the directors’ report, approved by the board in the same way as the financial statements.
Year two: Scope 3 emissions, and assurance by your auditors. The systems you build in year one need to hold up to review.
What it means for your first deadline
| Your phase | June 30 year-end | December 31 year-end |
|---|---|---|
| Phase I | First report covers the year to June 30, 2026; due by March 31, 2027 | Covers the year to December 31, 2026; due by September 30, 2027 |
| Phase II | Covers the year to June 30, 2027; due by March 31, 2028 | Covers the year to December 31, 2027; due by September 30, 2028 |
| Phase III | Covers the year to June 30, 2028; due by March 31, 2029 | Covers the year to December 31, 2028; due by September 30, 2029 |
Phase I
June 30 year-end: first report covers the year to June 30, 2026; due by March 31, 2027.
December 31 year-end: covers the year to December 31, 2026; due by September 30, 2027.
Phase II
June 30 year-end: covers the year to June 30, 2027; due by March 31, 2028.
December 31 year-end: covers the year to December 31, 2027; due by September 30, 2028.
Phase III
June 30 year-end: covers the year to June 30, 2028; due by March 31, 2029.
December 31 year-end: covers the year to December 31, 2028; due by September 30, 2029.
Source SECP, Order: Adoption of Sustainability Disclosure Standards, December 31, 2024
Dates are calculated from the Order.